Client
The Highland Council
Designer / Consultancy
AECOM
Construction Period
October 2023 – Ongoing
Budget
£1-5m
Project Overview
The works comprise the construction of a new segregated contraflow cycle lane and footway as part of the Inverness City Active Travel Network (ICATN) Route 2 on the Riverside Way between Eden Court and Bught Park.
Key Numbers
- Approx. 600m of drainage works.
- Milling – 6030m2.
- Carriageway and footway resurfacing – Carriage way – 2603m2; Footpath – 4139m2; Cycle path in Green SMA – 2151m2.
- 3343m of kerbing.
- Installation of 3 raised tables.
- Associated infrastructure, road signing and carriageway markings.
- Removal of and replacement of 70 lighting columns in conjunction with The Highland Council who will complete electrical work associated with street lighting.