Project Overview

Client

Kerry County Council

Client’s Representative

Jacobs

Construction Period

November 2021 – June 2024

Budget

€30-40m

Project Overview

The road development consists of the realignment of a section of the N69 and is approx. 6km in length. The scheme included approx. 4km of a new single carriageway and approx. 2.5km of online improvements to the exiting R533 (John B Keane Road) with enhanced pedestrian and cycle facilities. The project also included three roundabouts and a considerable amount of offline works and associated works were also carried out.

Snagging works of both the mainline and offline section are currently being closed off. Accommodation works for the locals along with additional change orders are currently being completed now that the road is opening. The compiling of the safety file is well underway which will form part of the handover. Kerry County Council are very happy with the new development and have thanked and praised the hard work by all Wills staff and subcontractors since the project began.

Key Numbers

  • 3x new roundabout junctions and associated improvements to regional and local roads
  • 19x structures, including a new bridge spanning the River Feale, tied sheet pile wall, accommodation underpasses, flood culverts and watercourse crossings
  • Urban realm improvements and an upgrade of vulnerable road user facilities on John B. Keane Road
  • Working within, and adjacent to, designated areas
  • Site clearance, drainage, earthworks, pavement, safety barriers, signing and lining, public lighting, utilities diversions, fencing and boundary treatments, accommodation works and bespoke landscaping