Client
Meta (Facebook)
J Coffey Construction Ltd
Designer / Consultancy
Mace
Construction Period
November 2017 –
November 2018
Budget
€20-50m
Project Overview
Wills Bros Group were appointed Civil Engineering Contractor. We provided management staff which included attending Monthly Project Progress meetings, attending Daily Activity Briefings (DAB) with all other stakeholders and contractors on site, provision of SPA (safe plans of action) for all activities undertaken. Programme reviews were undertaken weekly, and measures taken to ensure critical path activities were maintained. This resulted in all project milestones being achieved throughout the Project.
WBG undertook and gained approval of temporary works design for the works to hand. WBG also undertook Precast Concrete elements entailing mainly precast large sized services chambers for Multi bank fibre optics and MV, LV cabling. This, therefore, involved the Design, procurement, supply and Installation of the utility’s chambers and connections thereto.
WBG provided a full time Health and safety Officer on site. Audits were undertaken regularly and actions arising dealt with promptly, promoting and encouraging a positive safety culture on site in conjunction with all other Contractors and Client on site
WBG provided a full time BIM accredited Design and Engineering Co-ordinator. Latest Design Documents were issued through our BIM accredited Design Co-ordinator.
Navisworks was used to review the Federated model. Clash detection and opening the model in various 3D formats was used for clear understanding of scope. The model was used to create all setting out files for the 7 full time Site setting out Engineers. The model was updated weekly with all as built information provided by site Engineering staff. This was then fully collated and updated by our Design Co-ordinator and an updated version returned to the Client weekly.
Key Numbers
- 2000m of polysewer foul water installation
- 1700m of 29/32 x way fibre ducting installation
- 5500m of polysewer surface water pipe installation
- 60x precast foul water and surface water chambers
- 1600m of 150mm/355mm HDPE watermain installation
- 900m of 13x way LV ducting installation
- 1400m of 6x way MV ducting installation
- 72x precast concrete chambers for MV/LV/watermain chambers
- Approx. 1000m of Precast concrete ground beams
- 7000m3 of insitu concrete foundation pads
- 13,000m2 insitu concrete generator yard slab, with numerous plinths and upstands
- 800m2 sloped dock leveler yard slab with a circular plinth
- 350m2 of grasscrete paving cast insitu with GC2 formers
- 2x D4000 terminal pumping stations to a depth of 5m, including kiosks and pumps
- 2x versavoid core 700m3 attenuation tank