Project Overview

Client

Transport Scotland

Value

£35m

Duration

27 months

Designer

Atkins

Summary

Works involved the Design & Build of 7.5km dual carriageway between Kincraig and Dalraddy as part of the wider A9 Dualling Programme to improve the A9 between Perth and Inverness.

Key Numbers

  • 5km of online dualling of an existing single carriageway to dual carriageway standard
  • 11km of accommodation tracks between 2m and 4m
  • 7km of Non-motorised user tracks
  • 8x primary bridge structures including 2 road and river bridges
  • 7x secondary bridge structures
  • 15,000 m of filter drains (21 km in total)
  • 60,49 7m3 of topsoil strip
  • 6x major RC underpasses
  • Earthworks involving over 300,000 m of excavation processing
  • Road markings, signing
  • 11km of secondary access tracks
  • Environmental and ecological mitigation measures
  • Semi-flexible and fully flexible pavement batch on site