Project Overview

Client

The Highland Council

Construction Period

6 months

Budget

£0.5m

Project Overview

The Cycling, Walking, and Safer Streets at Strathdearn Primary School projects comprised the construction of footpaths, build-outs, drainage systems, the supply and installation of traffic signs and road markings, and the installation of street lighting.

Read more about Strathdearn Primary School in Tomatin here.

Key Numbers

  • 81m2 of flexible pavement for landowner access
  • New and Improved 420m combined footway and cycleways
  • 200m of permanent road markings
  • 250m of filter drains with inspection chambers
  • 150m of retaining walls
  • 420m2  of seeded grassed verges
  • 3x traffic calming measures
  • 3x drainage soakaways
  • Community benefit works for adjacent landowners