Project Overview

Client

The Highland Council

Designer / Consultancy

Capita

Construction Period

May 2016 – December 2017

Budget

£22.5m

Inverness Westlink

Project Overview

The construction of Roads and Bridgeworks from Holm Roundabout (B862 Dores Road) to A82 Glenurquhart Road comprised of 2km of 7.3m wide single carriageway road, 4 roundabouts, 2 underpasses and a new three span bridge over the River Ness. All with associated drainage, earthworks, fencing and walls, landscaping, new access tracks/paths, road lighting, car park and coach turning area along with the installation of new services and supplies.

The Canal Parks Enhancement Clubhouse included a new 8 room two-storey changing and clubhouse facility along with the installation of new services/supplies.

The construction of Canal Parks Enhancement Rugby Pitches comprising a new all-weather pitch to International Rugby Board standards and two grass pitches, boundary fencing, ball stop fencing and pitch lighting along with the installation of drainage and new electrical services/supplies.

Key Numbers

  • 2km of brand new, 7.3m wide single carriageway road
  • 4 roundabouts
  • A new, 171m long, three-span bridge over the River Ness
  • 2 underpasses
  • 30,000m2 of flexible pavement
  • 12km fencing
  • 218,000m2 site clearance
  • 10km road lining