A92 Eden Bridge Drainage Works

Carriageway and drainage works carried out on the A92 in Fife from the Eden Bridge southbound.


Earthworks to strengthen carriageway foundations. It involved excavations up to 2-3m deep and backfilling to old ditch, incorporating installation of new drainage systems. This project also included reconstruction of the carriageway


The project consisted of a lane closure for 23 days to allow completion of the works.
 

A92 Eden Bridge Drainage Works Project Team:
Client - Transport Scotland

Engineers - Bear Scotland Ltd

Contract Value:
300,000

References:
Transport Scotland
Trunk Roads Network Management Directorate
Buchanan House
58 Port Dundas Road
Glasgow
G4 0HF

Resident Engineer (Bear) Mr Scot Marshall

Project Engineer
Mr. Eddie Ross
Bear Scotland Ltd
Bear House
Inveralmond Road
Inve

Construction Period:
March 2011