Holmestown Waste Management Facility Landfill Cell Development Phase 2

The Phase 2 works consist of the construction of engineered landfill cells with a footprint area approximately 17,500 m². Works will include excavation of 77,000 m³ insitu clay material, placement of approximately 15,500 m³ engineered clay, approximately 16,000 m² HDPE liners and approximately 3,850 m³ of 500 mm drainage blanket),Leachate drainage and re-circulation system. Leachate rising main extension, Gas collection system extension, Ducts for power, telemetry, CCTV etc, Screening berm works, Upgrade of the eastern track to serve as the main haul road to Phase 1 landfill, Earthworks to the north of Phase 1.

Holmestown Waste Management Facility Landfill Cell Development Phase 2 Project Team:
Wexford County Council

Contract Value:
1,179,964.00

Construction Period:
June 2010