Microsoft Campus Development

The Development is for a new Campus for Microsoft located within the existing South County Business Park, Leopardstown, Dublin 18.

The Enabling works consisted of erection of 800m of timber hoarding, topsoil strip, the excavation of approx. 65000m3 of material including breaking of rock. Grade to formation level. Excavate for 1000m of drainage, lift cores, pits, substation & pad foundations. All formation was blinded with concrete. Works also included construction of two reinforced retaining walls, the dynamic compaction of 4500m2 of ground and placement of 600mm of capping over this ground. Concrete thickening to a suspended slab which consisted of concrete being brought up from intact rock 4-5m deep. 

Microsoft Campus Development Project Team:
Client: Microsoft Ireland

Construction Period:
April 2015 - August 2015